Project VATHILAKKOS PV11 Connection to the Grid
On Tuesday, May 30, 2023, project VATHILAKKOS PV11, with a power of 499,79 kW, was successfully connected to the electric grid of HEDNO. Multiple tests and measurements will be performed…
northwestco
On May 28, the Terms of Connection for the project VATHILAKKOS PV11 were received. The project is now ready to be constructed. VATHILAKKOS PV11, part of the energy community NORTHWESTCO Ε. ΚΟΙΝ., is located in the Municipality Servion, in the Regional Unit Kozanis, and has a power of 499,79 kW. It consists one of the 9 projects of NORTHWESTCO Ε. ΚΟΙΝ. that are ready to be constructed.